March 1, 2021 Construction Updates

Date: March 2, 2021
Category: Blogs construction
The gallery was not found!
NOTES ON CONSTRUCTION:

Cottages 4, 3, 2 and 1 concrete structures are finishing up:

  • Cottages 4, 3 and 2 support beam formwork has been removed and the precast panel and stairs have been installed.
  • Cottage 1 support beam formwork has been removed and the post shoring is in place. Waiting on the concrete break tests before removing the post shoring.

Restaurant/Ramp are well underway:

  • Ramp and bridge trenching is underway. Rebar placement has started.
  • Restaurant trenching and rebar placement has started.