Brief site update:

Cottages 4, 3, 2 and 1 are progressing with the following highlights

  • Cottage 4 support beam formwork has been removed and Gates is working on cleaning up the finishes from the concrete slag.
  • Cottage 3 support beam formwork has been removed and the post shoring is in place. Waiting on the concrete break tests before removing the post shoring.
  • Cottage 2 was being poured with concrete at time of visit. Anticipate stripping forms on Tuesday.
  • Cottage 1 support beams are in process of rebar being installed with an anticipated concrete pour date of 2/22/21.
  • Ramp and bridge trenching has started
  • Restaurant trenching has started in anticipation of NPS review of documents to be resubmitted once received.