Brief site update:
Cottages 4, 3 and 2 and 1 are progressing with the following highlights
- Cottage 4 support beam formwork has been removed and the post shoring is in place. Gates is working on cleaning up the finishes from the concrete slag.
- Cottage 3 support beams were poured. The concrete break tests were received allowing the platform removal to commence on 2/5/21.
- Cottage 2 support beams are in process of rebar being installed with an anticipated concrete pour date of 2/11/21
- Cottage 1 support beam platform is commencing
- Ramp and bridge trenching has started
- Restaurant trenching has started in anticipation of NPS review of documents to be resubmitted by COB 2/5/21