Monthly Archives: March 2021

March 23, 2021 Update

Containers being moved to factory in Durant

Learn more

March 11, 2021 Construction Updates

Brief site update: Cottages Buildings 4, 3, & 2 concrete structures are complete including the precast stairs and planks with the exception of cleaning up the concrete surfaces of any […]

Learn more

March 1, 2021 Construction Updates

NOTES ON CONSTRUCTION: Cottages 4, 3, 2 and 1 concrete structures are finishing up: Cottages 4, 3 and 2 support beam formwork has been removed and the precast panel and […]

Learn more