February 18, 2021 Update
Brief site update: Cottages 4, 3, 2 and 1 are progressing with the following highlights Cottage 4 support beam formwork has been removed and Gates is working on cleaning up the finishes from the concrete slag. Cottage 3 support beam formwork has been removed and the post shoring is in place. Waiting on the concrete …